A West End strip-out
What we did for a specialist studio builder.
A specialist studio builder was stripping out a West End building. The job had a lot of material to move and no room for a skip. The waste was mixed construction and demolition material, about a tonne a load.
The crew staged the waste on the pavement and loaded the cage each time our tipper arrived. We started with a trial day of two full loads. We then agreed two collection windows a day and ran two full loads a day at the peak, four days a week, about 30 full loads in all. We confirmed the times in writing.
Plasterboard and insulation were kept separate inside the cage and loaded last. Each load left with its own Waste Transfer Note and was invoiced per collection.
The job in three lines
- Volume. About 30 full loads in all.
- Schedule. Two loads a day at the peak, four days a week, inside two agreed windows.
- Streams. Mixed strip-out waste, with plasterboard and insulation separate and loaded last.